Did you know the KDL – Cascade Township Branch and the Township have partnered to provide library and recreational services in the current location for more than 25 years?

Though the library grounds were ocassionally used for programming and Township events, the outdoor space presented many challenges. Near the library building, the grass is frequently wet from rain and watering, resulting in water pools and puddles. The broader grassy space frequently dries out and provides the perfect habitat for ant colonies, making it less than ideal for sitting.
 
For years Friends of the Cascade Library has collected money from their regular book sales, Chapter Two Bookstore, and eBay shop to fund an outdoor gathering space. The group paid for an initial outdoor space master plan and, following bids from several companies, selected Native Edge to design a space where:

  • People could gather safely, surrounded by nature.
  • Larger events could be held.
  • Special events such as concerts could be hosted.
  • People, particularly children, could learn and explore.
  • Community members could picnic.
  • Environmental stewardship would be considered.

 The master plan was divided into three main phases of work:

  • Phase One included the area nearest the library and called for accessible sidewalks for easy traveling to a story time meeting space and a picnic area, featuring native plants and water gardens. It also included exploratory pathways into the existing wooded area.
  • Phase Two expanded the sidewalk beyond the woods and added more green space for gathering or lawn games and a pavilion.
  • Phase Three extended the sidewalk entirely around the building and created additional native plant areas and smaller tabled spaces for eating, studying, and socializing.

All phases of construction are now complete.

For further questions related to Friendship Park, call Parks & Facilities Director Zwick at (616) 949-1500 or email him at dzwick@cascadetwp.com.

pdf iconClick to view Friendship Park Site Plan (as of 10/30/23)
pdf iconClick to view Phase I-IV Cost Estimates (as of 4/18/23)
pdf iconClick to view Pavilion Plan
pdf iconClick to view Pavilion Plan Cost Estimate